Background Image
Table of Contents Table of Contents
Previous Page  277 / 300 Next Page
Information
Show Menu
Previous Page 277 / 300 Next Page
Page Background

Furse, Wilford Road, Nottingham, NG2 1EB • Tel: +44 (0)115 964 3700 • Email:

enquiry@furse.com

• Web:

www.furse.com

TSC-0912 - 09.10.12

BS EN/IEC 62305-3

Guide to BS EN/IEC 62305

can be decided at the early construction stage by using

dedicated reinforcing bars or alternatively to run a

dedicated copper conductor from the top of the

structure to the foundation prior to the pouring of the

concrete. This dedicated copper conductor should be

bonded to the adjoining/adjacent reinforcing bars

periodically.

If there is doubt as to the route and continuity of the

reinforcing bars within existing structures then an

external down conductor system should be installed.

These should ideally be bonded into the reinforcing

network of the structures at the top and bottom of

the structure.

Down conductors

Down conductors should within the bounds of

practical constraints take the most direct route from

the air termination system to the earth termination

system. The greater the number of down conductors

the better the lightning current is shared between

them. This is enhanced further by equipotential

bonding to the conductive parts of the structure.

Lateral connections sometimes referred to as coronal

bands or ring conductors provided either by fortuitous

metalwork or external conductors at regular intervals

are also encouraged. The down conductor spacing

should correspond with the relevant class of LPS (see

Table 11).

There should always be a minimum of two down

conductors distributed around the perimeter of the

structure. Down conductors should wherever possible

be installed at each exposed corner of the structure as

research has shown these to carry the major part of the

lightning current.

Natural components

BS EN/IEC 62305, like BS 6651, encourages the use of

fortuitous metal parts on or within the structure to be

incorporated into the LPS.

Where BS 6651 encouraged an electrical continuity when

using reinforcing bars located in concrete structures, so

too does BS EN/IEC 62305-3. Additionally, it states that

reinforcing bars are welded, clamped with suitable

connection components or overlapped a minimum of 20

times the rebar diameter. This is to ensure that those

reinforcing bars likely to carry lightning currents have

secure connections from one length to the next.

When internal reinforcing bars are required to be

connected to external down conductors or earthing

network either of the arrangements shown in

Figure 20 is suitable. If the connection from the

bonding conductor to the rebar is to be encased in

concrete then the standard recommends that two

clamps are used, one connected to one length of rebar

and the other to a different length of rebar. The joints

should then be encased by a moisture inhibiting

compound such as Denso tape.

If the reinforcing bars (or structural steel frames) are to

be used as down conductors then electrical continuity

should be ascertained from the air termination system

to the earthing system. For new build structures this

Class of LPS

Typical distances (m)

I

10

II

10

III

15

IV

20

Table 11: Typical values of the distance between down conductors

according to the Class of LPS (BS EN/IEC 62305-3 Table 4)

Figure 20: Typical methods of bonding to steel reinforcement

within concrete

Stranded copper cable

(70 mm

2

PVC insulated)

Cast in

non−ferrous

bonding

point

Bonding conductor

Clamped cable to rebar

connection

Steel reinforcement within

concrete (rebar)