D-94

Additional information

Practical information

Dd381541.eps

Handling by the top

If cranes or overhead hoists are used, only slings that are sufficiently strong

and in good condition should be used.

b

The slings must be attached to the 4 cubicle lifting lugs.

b

Adjust the length of the slings according to the switchboard dimensions so that the

angle formed does not exceed the angle indicated below depending on the

switchboard weight. When 2 switchgear cubicles are combined, a lifting beam must

be used.

b

Never tilt the cubicle during handling.

b

Take care to equally distribute the load on the 4 rings.

DD383915.eps

DD210574.eps

Position of lifting rings

The lifting rings can be installed and removed without dismantling the roof.

Even with the lifting rings permanently installed, the switchboard retains its original

degree of protection.

For combined cubicles, only install lifting rings on cubicles with switchgear.

DD383379.eps

DD383916.eps

Lifting several cubicles packed together

In the special case of an assembly with more than 2 cubicles, you must:

bb

first of all move the assembly in its original packing as close as possible to where

it is to be installed

bb

use a lifting beam and slings to support the switchboard from underneath.

Handling on the site