Table of Contents Table of Contents
Previous Page  46 / 356 Next Page
Information
Show Menu
Previous Page 46 / 356 Next Page
Page Background

44

9 - Insulation resistance and dielectric test

To carry out either of these tests:

all electrical equipment must be connected (except those apparatus which are

designed for a lower test voltage)

the test voltage must be applied:

between each pole and the interconnected exposed conductive parts

between each pole of the main circuit and the other poles

between each auxiliary control circuit and the main circuit and the exposed

conductive parts

between the power side and the withdrawable part of a switchgear in

disconnected position.

Insulation test:

insulation measurement using an insulation measuring device at a

voltage of at least 500V (e.g. Megger type tester).

The test is passed if there is no puncture or disruptive discharge between the

different tested parts

Dielectric test:

for a rated operational voltage of 40/400 V, the dielectric test

voltage of 500 V must be applied during 1 s.

The test is passed if the insulation resistance between circuits and exposed

conductive parts is at least 1000 Ohms/V.

10 - Protective measures

This test involves checking the electrical continuity of the protective circuit

connecting the various metal assemblies.

The presence of barriers protecting against direct and indirect contact with live parts

must be checked and the following points must be inspected visually:

the presence of earthing wires on the doors

the presence of the PE conductor and contact washers on all metal assemblies.

b

b

v

v

v

v

b

b

PD3909 9

PD390914

Once the tests have been completed, the following operations must be carried out :

clean the inside of the switchboard

check that the switchboard identification markings are present

check the outside appearance (scratches, paintwork, etc.)

prepare the reports.

The first report must list any missing components or equipment that will be shipped

separately from the switchboard.

The second report must indicate any problems detected during testing and the

corrective action required.

A test report (available from the panelbuilder) certifies that all the tests have been

carried out.

b

b

b

b

DD3839 0

Prisma Plus

tested switchboards

Standards and

Prisma Plus tested

switchboards