7
DB118815
Circuit-breaker
Contactor
Circuit-breaker
Contactor
Load
Load
Kilowatt-hour meter
Kilowatt-hour meter
Example: meter on a load switching
Installation
b
b
The front panel of the product is IP40 and its housing is IP20.
b
b
Its installation must be appropriate to the operating conditions.
b
b
The protection must not be less than IP65 for outdoor use.
Use with a contactor
Ameasurement instrument is normally continually supplied.
For a non-continuous supply (load switching), we recommend that you place the
breaking device downstream from the measurement instrument to limit disturbances
on the module inputs.
These disturbances, particularly on inductive loads, may result in early ageing of the
device.
You must also place the measurement instrument at a distance from the breaking
device to limit the risk of disturbance.
Specific technical data
iEM2000, iEM2010, iEM2000T, iME1, iME1z and iME1zr specific technical data
iEM2000 iEM2010 iEM2000T
iME1
iME1z iME1zr
Direct measurement
Up to 40 A
Up to 63 A
Metering and activity indicator light
(yellow)
3,200 flashes per kWh
1,000 flashes per kWh
Wiring error indicator
Yes
Total meter (max. capacity) on one
phase
999 999.9 kWh
999.99 MWh
Total meter display
In kWh with 7 significant digits (not for iEM2000T)
In kWh or MWh with 5 significant digits. No decimal point in
kWh; 2 digits after the decimal point in MWh
Partial meter (max. capacity) on one
phase with RESET
-
-
99.99 MWh
Partial meter display
-
-
In kWh or MWh with 4 significant digits. No
decimal point in kWh; 2 digits after the decimal
point in MWh
Remote transfer
-
By static output:
- ELV insulation voltage: 4 kV, 50 Hz
- 20 mA/35 V DC max.
- 100 impulses of 120 ms per kWh
-
-
By NO impulse contact:
- ELV insulation voltage: 4 kV, 50 Hz
- 18 mA/24 V DC, 100 mA/230 V AC
- 1 impulse of 200 ms (contact
closing) per kWh
Connection
Single-phase circuit
DB118858
DB118858
to impulse meter
(iME1zr)
iEM2010
iME1 / iME1z / iME1zr.
Caution
b
b
Do not earth the CT secondary (S2).
b
b
You must comply with the routing direction of power cables in the current
transformer primary. Cables enter in "P1" and leave in "P2" to the loads.
DB114265
DB114264
1