Background Image
Table of Contents Table of Contents
Previous Page  534 / 582 Next Page
Information
Show Menu
Previous Page 534 / 582 Next Page
Page Background

Appendix

Glossary

15/8

Siemens ET B1 · 10/2008

15

Inrush current

Current peak when switching on transformers or switching mo-

tors on and off. Caused by electromagnetic transient reactions

(

inrush effect) when the magnetic field is set up. The current

peak can take the following values for motors at the rated

voltage:

On-switching:

I

max

=

I

on

* (1.8

to 2.0),

Star-delta time transfer:

I

max

=

I

on

* (2.1

to 3.7),

Reversing:

I

max

=

I

on

* (2.7

to 5.0).

With transformers, the inrush current (starting current) depends

on the design, version, winding construction, application, power

rating, etc. as r.m.s. value is approx. 15 to 30 times the primary

rated current.

The inrush current dies down very quickly and is considerably

smaller after just 20 ms.

Insulation monitoring

Measure that monitors the insulation resistance of an electrical

system of a measuring device of which neither an outer conduc-

tor nor a neutral point is directly grounded. Any insulation fault

that occurs is indicated or, if a second fault occurs, the electrical

system may be switched off.

Insulation resistance

The smallest resistance that is measured between components

that are insulated from each other – or between these and the

ground.

Let-through current

I

D

The largest instantaneous value of the current during the OFF

time of a switching device or fuse. Limited short-circuit currents

occur when the switching device, e.g. as result of resistance,

operating delay and peak arc voltage, lowers the amplitude of

the short-circuit current. The let-through current of a device (e.g.

current-limiting miniature circuit breakers) is decisive for the

thermal load (I²t-value) of downstream devices (current

limitation).

Live component

Conductive component of a device that is live under normal op-

erating conditions. This also includes the neutral conductor (N)

and conductive components that are connected to it. However,

this does not apply if the neutral conductor is also the PEN

conductor.

Load / current-using equipment

Devices or installations that convert electrical energy to another

non-electronic energy form. In the field of alternating current

technology, loads are divided into three categories:

Resistive loads that do not cause phase displacement be-

tween current and voltage in the system, e.g. heating, incan-

descent lamps.

Inductive loads that cause the current to lag behind the volt-

age, e.g. motors, coils, electromagnets.

Capacitive loads that cause the current to lead the voltage,

e.g. capacitors.

Loop impedance

The impedance of a fault loop is the sum of the impedances (ap-

parent resistances) in a current loop, comprising the impedance

of the power source, the impedance of the outer conductor from

one pole of the power source to the measuring point and the im-

pedance of the return conductor (e.g.protective conductor,

ground electrode and ground) from the measuring point to the

other pole of the power source.

Main circuit

Circuit that contains devices that generate, convert, distribute,

switch and pick-up electrical energy.

Making capacity

The value of the prospective starting current, which can switch

on a switching device under the prescribed conditions at a

specified voltage

Melting time

The time required to melt the fuse element of a fuse link, from the

start of the non-permissible overload current or short-circuit cur-

rent through to the start of the interruption process.

Meshed network

The meshed network is used to distribute energy over a cable

system with a network-like topology. The power is generally in-

fed over a number of points. If a cable fails, each load is auto-

matically fed (no need for switchover) over the remaining cable

branches (radial network, ring network).

Miniature circuit breakers

Mechanical switching device that serves to manually connect or

disconnect a circuit according to the mains and automatically

disconnect the circuit from the mains if the current exceeds a

specific maximum value.

In the event of the thermal overload of a connected load or

branch, a thermally delayed release initiates the switch-off pro-

cess. In the event of a short circuit, the instantaneous short-cir-

cuit release takes over disconnection. Both releases function in-

dependently of each other and protect each other. The release-

free mechanism of the miniature circuit breaker ensures that the

switch trips in the case of overcurrent and short circuit, even if

the actuating lever is jammed in one setting or is held in place

by an operator. In order to provide optimum branch protection,

the miniature circuit breakers are produced with several different

tripping characteristics (B, C and D).

Modular width (MW)

The width of modular devices is specified at n (

)

mm,

whereby n=0.5; 1.0; 1.5; 2.0; 2.5… is possible.

A modular width (MW) is 18 mm (17.5 + 0.5 mm) and the mount-

ing width n * 18 mm, available for modular devices. e.g. distribu-

tion boards.

Neutral conductor (N)

A conductor connected to the neutral or star point of the network

that is suitable for transmitting electrical energy.

N devices

Installation devices according to DIN 43830, with a mounting

depth of max. 55 mm.

N distribution boards

Small distribution boards according to DIN 43871 with a small

mounting depth for N devices up to 63 A.

No-load voltage U

0

Output voltage of an unloaded transformer at the rated input

voltage and rated frequency.

OFF time

Duration from the start of the command output to open a switch-

ing device through to the final extinguishing of the electric arcs

(

ON and OFF time).

ON or OFF time

Duration from the start of the command output to switch a

switching device ON or OFF until the current is flowing uniformly

in all poles, or is no longer flowing.

When connecting to a short-circuit current, the time that elapses

from the moment the response current of a release is reached to

the time when the electric arc is extinguished in all poles.

2

2

2

17,5

+0,5

-0

© Siemens AG 2008